← Cedar Peak Medical Office — Phase 2 Project Summary

Compare versions

2 changed lines
Cedar Peak Medical Office — Phase 2 Owner: Cedar Peak Medical Partners · Architect: Stanton + Reyes Architecture Value: $14.2M GMP · Duration: 14 months · Status: Contract sent 2026-07-01 Scope 42,000 SF medical office over one level of below-grade parking.
Structural steel, curtainwall on the south elevation, two OR-ready shell suites.
− Key risks - OR suite MEP coordination — Apex Mechanical engaged early for BIM - Curtainwall lead time is 22 weeks; release within 10 days of NTP - Below-grade waterproofing warranty requires manufacturer's inspector Team PM: Elena Vasquez · Super: Ray Donnelly · PX: Priya Shah See also the Bid Day Runbook /a/bid-day-runbook used on the Phase 1 pursuit.
+ Key risks - OR suite MEP coordination — Apex Mechanical engaged early for BIM - Curtainwall lead time is 22 weeks; release within 10 days of NTP - Below-grade waterproofing warranty requires manufacturer's inspector Team PM: Elena Vasquez · Super: Ray Donnelly · PX: Priya Shah See also the Bid Day Runbook /a/bid-day-runbook-f0565b used on the Phase 1 pursuit.