Raw sources (meetings, notes) distilled into facts. 3 items · 25 facts. ← Home
Weekly Ops Review — July 6
- Metric Larimer Fleet closeout punch list is down to 14 items
- Metric Final completion certificate for Larimer Fleet expected July 20 (due 2025-07-20)
- Metric Larimer final pay app collected for $634,900
- Metric Near-miss reporting hit 6.2 per 10k hours in June
- Note Zero recordables in June
- Action Dana to call Walsh about overdue payment from Bellhaven Development — Dana
- Metric Bellhaven Development owes $447K on the December TI job
- Action Backfill assistant super role on Foothills pursuit if won
- Person Ray Donnelly moves to Cedar Peak as super August 1 (due 2025-08-01)
- Metric Cash position is $3.1M operating
- Action Legal to review Cedar Peak contract and aim for signature by July 15 — Legal (due 2025-07-15)
Bellhaven Bid Review — July 2
- Metric Podium concrete cost with Vantage is $6.1M
- Metric Podium concrete cost with Rocky Mtn is $6.4M
- Decision Price the PT alternate separately
- Action Get Griffin Electric's updated podium number — Marcus (due 2025-07-09)
- Metric Average 11 days per pour cycle for the last three podium decks
Monday Precon Meeting — June 29
- Metric Backlog is $52M
- Metric Bonding headroom is $38M
- Decision Hold the 3.75% fee on Bellhaven
- Metric EMR renewal is 0.71
- Metric EMR renewal saves $90K a year in premium
- Action Find a second drywall source before Bellhaven buyout — Marcus
- Metric Cedar Peak retention has 5% retainage reducing to 2.5% at 50% complete
- Metric Summit Ridge K-8 go/no-go scored 78
- Action Submit proposal for Summit Ridge K-8 to the district — Marcus (due 2025-07-18)