Cedar Peak Medical Office — Phase 2
Owner: Cedar Peak Medical Partners · Architect: Stanton + Reyes Architecture Value: $14.2M GMP · Duration: 14 months · Status: Contract sent 2026-07-01
Scope
42,000 SF medical office over one level of below-grade parking. Structural steel, curtainwall on the south elevation, two OR-ready shell suites.
Key risks
- OR suite MEP coordination — Apex Mechanical engaged early for BIM
- Curtainwall lead time is 22 weeks; release within 10 days of NTP
- Below-grade waterproofing warranty requires manufacturer's inspector
Team
PM: Elena Vasquez · Super: Ray Donnelly · PX: Priya Shah
See also the Bid Day Runbook used on the Phase 1 pursuit.