Cedar Peak Medical Office — Phase 2 Project Summary

$14.2M medical office building, contract out for signature.

Version 2 · July 8, 2026 project
✏️ Click into the document to edit, then Save. Cancel

Cedar Peak Medical Office — Phase 2

Owner: Cedar Peak Medical Partners · Architect: Stanton + Reyes Architecture Value: $14.2M GMP · Duration: 14 months · Status: Contract sent 2026-07-01

Scope

42,000 SF medical office over one level of below-grade parking. Structural steel, curtainwall on the south elevation, two OR-ready shell suites.

Key risks

  • OR suite MEP coordination — Apex Mechanical engaged early for BIM
  • Curtainwall lead time is 22 weeks; release within 10 days of NTP
  • Below-grade waterproofing warranty requires manufacturer's inspector

Team

PM: Elena Vasquez · Super: Ray Donnelly · PX: Priya Shah

See also the Bid Day Runbook used on the Phase 1 pursuit.