Bid Day Runbook
T-48 hours
- Confirm all addenda acknowledged (list them on the form!)
- Bond request to surety — Tom signs
- Sub quote matrix: minimum 3 per major trade, flag scope gaps
T-4 hours
- Leveling meeting: Marcus + lead estimator level all major trades
- Plug numbers identified and circled — every plug needs a fallback sub
- Final margin call: Dana sets fee based on go/no-go score and backlog
T-60 minutes
- Two people fill the form independently, cross-check
- Phone lines open for late sub quotes — cutoff T-15
- Delivery confirmation (portal receipt or stamped hand delivery)
Post-bid (same day)
- Save final leveling sheet to the project folder
- If we're low: notify surety, start buyout list
- If not: log the spread in the bid results tracker — we mine this for pricing intel